Friday, December 21, 2007

Plumbing and Parking

Today work is continuing on the new building plumbing and the new front parking lot. The city inspector is expected today to look over the sewer lines before work can continue. The main pipes for the chiller (shown in the picture) are also being buried on the west side of the school building where the chiller yard will be.

On the Westheimer side they are now removing several inches of soil from the entire park area. Because there is no base they will need to carefully prepare the soil for the new parking lot. I understand that they will skim off about 5-6 inches of top soil and then spread lime which will then be covered with several inches of rock. During construction the parking lot will remain a gravel lot so that we do not damage the asphalt finish. Once work is completed on the building the parking lot will be paved.

No comments: