Drainage Work

The last couple of days the work site has been relatively peaceful, meaning the work is not happening at the speed it had been leading up to the final slab pour. Mostly the work has been focused on the huge amounts of underground storm drainage that still has to be installed. This work will probably continue for the next few weeks.

They are also doing a fair amount of cleaning up around the site; a lot of grade dirt being removed or leveled around the new building site.

This morning work began to remove the front and west entries to the sanctuary (removing the concrete steps and sidewalks). One more small inconvenience for the sake of progress.