Monday, January 7, 2008

Plumbing and Electric Work

Today the work is focusing on the west end of the new building. This end will house the youth room and the early start school classrooms. This means there is a lot of plumbing and electrical work that has to be done before the slab can be poured (planned for this Saturday). The plumbing is especially time consuming because the restrooms in the little classrooms are all floor drains (unlike the wall drains in the new restrooms in the commons). The new electrical main also comes off of the pole into the building on the west side so they are laying those lines too.

Otherwise the piers for the chiller pad were poured today.