There is no picture for today's post. On Friday and Saturday the sheet rock workers were busy sanding down the last of the rough spots. The interior walls (with a few exceptions) are now ready for the painters who will arrive on Monday morning.
The painting crew will prime the walls and then apply two coats of paint. The first coat will be done immediately and the final coat will be applied after all of the flooring and fixtures have been installed. This is being done so that the last coat of paint will be free from the bumps, dings, and dents that happen with so many people working inside the building. Also this week: tile work in the restrooms and EC classrooms; after a final inspection, ceiling tiles; more cabinetry installed; light fixture installation; final details completed in the youth room.